Improving and remodelling the I-595 Corridor Roadway in Florida (USA)

Juan Miguel PÉREZ RODRÍGUEZ
Executive Vice President y Project Manager de DRAGADOS USA

José Mª NAVARRO CALLEJA
Dirección Técnica DRAGADOS (28050 Madrid)

ABSTRACT 

In March 2014, 60 after months of design and construction work, dredging performed the last section of the first project of public-private partnership (PPP) in the state of Florida: the remodeling of the I-595.

The main challenge that DRAGADOS faced up was the construction of a new roadway within a corridor of high capacity, maintaining the level of traffic service, during all phases of the works, that were finally completed ahead of schedule.

It is important to highlight the operations carried out on the University Drive Interchange, in which, instead of demolishing the existing bridge, it was proposed to adapt its alignment and rise it 45 centimeters, improving safety, cost and time.

DRAGADOS developed an Environmental Compliance Plan (ECP) which included the rehabilitation of the North River Channel, and the construction of greenways along the entire route.

KEYWORDS:

Highway, Corridor, Remodelling, Estructure, Traffic, Public-private partnership, USA, Florida, Connection.

Asociación Española de la Carretera
Goya, 23 - 4º Right.
28001 - MADRID (Spain)
Tel .: (34) 91 5779972
E-mail: This e-mail address is being protected from spambots. You need JavaScript enabled to view it.

Cookies allow us to offer our services. By using our services, you agree to our use of cookies. See Cookies policy